Mooresville's Brawley School and Williamson Road Projects: Where Each One Stands

November 26, 2026

On November 5, 2026, the North Carolina Board of Transportation approved a change to the project list that most west Mooresville drivers will never read. It moved construction of the Fairview Road extension over I-77 from fiscal year 2027 to fiscal year 2029, and the listed reason is "to allow additional time for right-of-way acquisition." That one change sets the order of west Mooresville's road work. The Brawley School Road widening is due first, the two Williamson Road phases follow, and the Fairview bridge now comes last. The roads around Brawley School Road and Williamson Road will be finished in stages over several years, and the stretch you feel most depends on which side of that intersection your home sits on.

For a buyer comparing addresses on the peninsula and along Williamson Road, that order matters more than any single completion date. A family planning to stay ten years will see all of it finished. A buyer who expects to sell within four or five years could own the home through most of the construction and still list it while the Fairview bridge is being built.

The Schedule, Project by Project

Each date below comes from NCDOT, the Town of Mooresville or local news coverage of NCDOT's plans.

Project What it does Latest published schedule
R-3833C, Brawley School Road Widens Brawley School Road from I-77 Exit 35 to US 21 49% complete in NCDOT's April 2026 status report; early 2029 completion in NCDOT's release last updated Dec. 23, 2025
R-5100A, Williamson Road Widens Williamson Road to four lanes from I-77 to Brawley School Road Right-of-way acquisition underway, construction listed for 2027, April 2026
R-5100B, Williamson Road Widens Williamson Road to four lanes from Brawley School Road to NC 150 Construction funded fiscal 2027 through fiscal 2030, November 2026
U-5817, Fairview Road Extends Fairview Road over I-77 to Alcove Road, with connector roads to Williamson Road Construction moved to fiscal 2029, funded through fiscal 2033, November 2026
NC 150 widening Widens NC 150, with new bridges at I-77 Exit 36 and over Lake Norman First segment expected spring 2030, as reported by WCNC

Brawley School Road is the furthest along, Williamson Road is still in right-of-way and utility work, and the Fairview bridge is now the last to start. All three meet in one small area around Brawley School Road and Williamson Road.

The Intersection Where the Projects Meet

Brawley School Road runs east from Exit 35 toward downtown Mooresville and southwest down the peninsula toward Trump National Golf Club Charlotte and Lake Norman Yacht Club, according to the Charlotte Observer. Trump National sits inside The Point, whose owners association lists the golf club among the community's features, and the yacht club's address is 297 Yacht Road. Any home at that end of the peninsula reaches the interstate by the same road.

On that road, just west of Williamson Road, is the Publix-anchored Brawley Commons shopping center, as the Charlotte Observer described it in June 2026. Both Williamson Road phases end at Brawley School Road. Phase A runs south and west from there to I-77, and Phase B runs north to NC 150. Past that intersection, Brawley School Road reaches Exit 35, where the R-3833C widening starts and heads east to US 21.

So a peninsula address and a Williamson Road address can sit close together on a map and still feel the work in different years.

Peninsula Addresses Feel Brawley School Road First

R-3833C is the project peninsula drivers pass through on the way into town. The Town of Mooresville says construction began in June 2024 and lists a $51.1 million cost estimate. NCDOT's release calls it a $34.8 million job and describes the finished road as four lanes, divided, with U-turn bulbs, signalized intersections, bike lanes and sidewalks.

The U-turn bulbs change daily trips the most. On a divided road with U-turn bulbs, a driver leaving a side street often turns right and then makes a U-turn at a bulb instead of turning left across traffic. Before you commit to an address off this stretch, drive the trips you would make most often, such as school drop-off, the grocery run and the Exit 35 on-ramp. The route you drive this year may not be the route you drive in 2029.

The Exit 35 backup is a familiar local complaint. In September 2025, a longtime resident told WBTV that traffic from Exit 35 could take five or six signal cycles to clear. The project was 49% complete in April 2026, and NCDOT's most recent published target is early 2029. A peninsula buyer who closes this winter would live with roughly two more years of this work, if the target holds.

Williamson Road Addresses Have the Longest Construction Window

The Williamson Road corridor includes the Morrison Plantation shopping area, whose Harris Teeter is at 134 Town Center Drive. Construction there is mostly still ahead. WCNC reported that NCDOT expected the first phase, Brawley School Road to NC 150, to start in early 2027 at an estimated $10.5 million. It also reported the second phase, I-77 to Brawley School Road, to follow in fall 2027 at an estimated $74.3 million.

The November 2026 project list updated the northern phase. It shows R-5100B at $16.2 million, with construction funding spread from fiscal 2027 through fiscal 2030. The same entry flags a cost increase above the state's "$2 million and 25%" thresholds. The southern phase, R-5100A, was still in right-of-way acquisition in April 2026 with construction listed for 2027.

The Fairview Road extension is the last project in line. U-5817 would carry Fairview Road over I-77 to Alcove Road and build parallel north-south connector roads to Williamson Road. It would give this corridor a crossing of the interstate that does not depend on an exit ramp. Its $25.2 million construction funding now runs from fiscal 2029 through fiscal 2033. For a Williamson Road buyer, the first construction crews could arrive in 2027 and the last funded year falls in the early 2030s. That is the longest construction window of any address in this post.

Some buyers will weigh it the other way. A household that plans to stay in a Williamson Road home past the early 2030s would own it once the corridor has four lanes and a new crossing over I-77, and would have paid a price set while the work was underway.

Homes Near Exit 35

The parcels closest to the interchange have their own schedule. D.R. Horton has proposed up to 50 townhomes on 6.3 acres near Exit 35, with access through the streets of the existing Sunridge Place townhome community rather than directly from Brawley School Road. The Charlotte Observer reported that the Mooresville Planning Board recommended the rezoning 6 to 3 in August 2026. On October 19, the town board tabled the request for six months and asked staff to explore plan revisions and ask NCDOT again about a right-in, right-out access option, Lake Norman Publications reported. The request could return around April 2027.

Lake Norman Publications also reported that the new and proposed development in that area relies on Silver Hook Drive, which meets Brawley School Road at Rolling Hill Road about a third of a mile west of I-77. If you are looking at Sunridge Place or nearby Gibbs Cove, that intersection and the April 2027 town board meeting are both on the calendar that matters to you.

North-Side Trips Run Through Exit 36

Any trip north toward NC 150 has another work zone. On November 12, 2026, Country 103.7 reported I-77 lane closures at NC 150 Exit 36 for construction of a new 10-lane bridge. NCDOT's November 2026 project update lists asphalt work from US 21 to Williamson Road, weather permitting, along with continued I-77 traffic shifts for the bridge. WCNC reported that work on the new Lake Norman bridge was expected to begin by early 2027 and that the first segment of the NC 150 widening was expected in spring 2030.

The northern Williamson Road phase ends at NC 150. Homes at that end of the corridor sit next to two projects whose schedules overlap into 2030.

Matching the Schedule to How Long You Plan to Stay

Two homes with the same price, the same lot size and the same distance to the lake can come with different amounts of construction. Compare each candidate address with your expected holding period. A peninsula home bought this winter has about two more years of Brawley School Road work before the early-2029 target. A Williamson Road home has construction that has not started yet, with funding listed into fiscal 2030 for one phase and fiscal 2033 for the Fairview bridge. A home near Exit 36 shares the NC 150 schedule.

None of these dates is guaranteed. The November 5 change to the Fairview bridge shows how far a schedule can move in one board meeting. Use them as the published plan as of late 2026.

A Few Questions We Hear

Is the Fairview Road bridge canceled? No. The November 2026 project list keeps U-5817 funded at $25.2 million and moves its construction start to fiscal 2029.

Does the Brawley School Road widening run down the peninsula? R-3833C runs from I-77 Exit 35 east to US 21. Peninsula drivers reach it once they pass the interchange heading toward town.

Where can I check for updates? The Town of Mooresville posts closures and notices on its Transportation Updates page, and NCDOT posts NC 150 progress on its project page.

If you are choosing between the peninsula, Williamson Road and the streets near Exit 36, we can go through each address against these project schedules and your plans for the home. Call Foster Rojahn Premier Properties or request a free home valuation and consultation, and Jennifer Foster or Barrie Rojahn will help you match the address to how long you plan to stay.